assignment 2336

Directions

To complete this assignment, refer to the Hudson Jewelers case study using OM6 Online Access.

Exhibit 18:20 Hudson Jewelers Case Work Breakdown Structure (download Project Management Assignment file) shows the project work activities for designing costume jewelry using computer-aided design (CAD). Draw the network diagram, determine the project completion time and critical path(s), as well as the activity slack times. In addition, create a Gantt chart for the project, and then summarize your insights.

Submission

This assignment requires a file upload submission. After you have reviewed the assignment instructions and rubric, as applicable, complete your submission by selecting the Submit Assignment button next to the assignment title. Browse for your file and remember to select the Submit Assignment button below the file to complete your submission. Review the confirmation annotation that presents after submission.

Exhibit 18:20 Hudson Jewelers Case Work Breakdown Structure

Activity

Immediate Predecessors

Activity Times (Days)

Start

Co-design

  1. Conceptualize Design

————————————-

3

  1. Deposit Made

————————————–

2

  1. CAD Program

A

2

  1. CAM Process

A

2

Payment

  1. Payment Balance

B

3

Manufacturing

  1. Lost-Wax Casting Process

C,D

6

  1. Finishing By Hand

D, E

2

  1. Final Polish

G

2

Deliver

  1. Quality Control & Inspection

F

3

  1. Packaging

I

2

  1. End Costumer Delivery

H, J

1